RFI form for earthwork activities, itemized by numbered work items, routed for direct RE/RTO verification.
Details
Site Engineer/Supervisor submits RFI No, requested date/time, drawing reference, and general description/location, listing up to 9 numbered items & descriptions. Contractor checks each item first, then routes directly to RE/RTO Inspector for verification.